At Dori the borehole is cut by core drilling and lined with steel casing.

Artesian well drilling in Dori

Location and Country: Dori, Sahel Region · Burkina Faso

Responsible organization:Idrogea Water Cooperation

The initiative addresses the chronic water deficit in Séno province, where rural residents currently travel over eight kilometres to access uncontaminated groundwater. The works encompass geotechnical drilling down to 95 metres, stainless steel casing, and the commissioning of a submersible pump powered by solar arrays.

Daily operation is managed by a village water committee trained in flow monitoring and valve servicing. Water is piped to an elevated 15,000-litre storage tank connected to four public distribution stands serving both local households and pastoral herds.

Hydrogeological surveys completed prior to excavation confirmed groundwater resilience, with an estimated steady yield of 4.5 cubic metres per hour even during peak dry season conditions.

Declared progress

74 metres of well drilled of 95 planned · 78%
Estimated unit cost€85/ metres of well drilled
Total expected cost€8,075(planned)

Operational update timeline

Chronological log of field dispatches, itemized expenditures, and delivered units per milestone.

  1. Casing installation completed and pump flow test at 74 metres

    Field engineers concluded slotted screen pipe lowering and initiated a 24-hour continuous pumping run to clear fine sediment from the aquifer.

    Units delivered in this phase: 24 metres of well drilled Reported expenditure in this update: €2,800
  2. Mechanical drilling advanced to 50-metre depth

    The rotary rig penetrated the upper granite layer and contacted the primary semi-confined water table.

    Units delivered in this phase: 30 metres of well drilled Reported expenditure in this update: €4,250
  3. Site mobilization and initial hydrogeological sounding

    Delivery of the tracked drilling unit to municipal land and demarcation of the safety perimeter agreed with local elders.

    Units delivered in this phase: 20 metres of well drilled Reported expenditure in this update: €1,700